Evaluate the Relationships Between Durations And/Or Costs

The Risk Sensitivity chart evaluates the relationship between durations and/or costs by creating a scatter chart showing their interaction.

To run the Risk Sensitivity chart, complete the following steps:

  1. Select the S3 // Risk tab.
  2. In the Views group, click Right Panel > Risk Sensitivity.
  3. On the Risk Sensitivity configuration screen, select X and Y axis activities and values for each activity to view their relationship.
  4. Click Analyze to create the Risk Sensitivity chart.